The Release Manager creates and modifies the structure of release activities by performing the following steps.
To plan release activities
-
In the Service Manager console, open the Work Items workspace, and in the Work Items pane expand Release Management and then select Release Management.
-
In the Work Items pane, select a view under Release Management that displays a release record that includes release activities that you want to add or modify activities for and then double-click the record to open it.
-
Click the Activities tab to view the list of proposed changes and dependent activities they contain.
-
Optionally, you can change the activities view by clicking either Diagram View or List View.
-
Select a dependent change management activity and move it to the top of release management activity list or diagram. A dependent indicator appears both on the change and release management activities.